Legal Counsel Heriberto Morales did specify that negotiations would be taking place with the company.
“If we can’t negotiate a contract with that company then we will move and begin negotiations with the company that came in second in the rating system,” said Morales.
The city has seen legal issues regarding the Eagle Pass Public Safety Headquarters regarding performance issues related to Gignac and Associates, LLP, in the development of the Public Safety Headquarters among other set backs that have come up.
The Public Safety headquarters construction is almost 8 months behind schedule due to those unforeseen fallouts.
De La Garza Construction encargados de construcción en edificio de Seguridad Pública
Durante la reunión del Concilio de la Ciudad celebrada el pasado martes, la ciudad eligió a De La Garza Construction como el nuevo Gerente de Construcción de la Sede de Seguridad Pública.
El consejero legal Heriberto Morales sí especificó que las negociaciones se llevarían a cabo con la empresa.
"Si no podemos negociar un contrato con esa compañía, nos moveremos y comenzaremos las negociaciones con la empresa que quedó en segundo lugar en el sistema de calificación", dijo Morales.
La ciudad ha visto problemas legales con respecto a la Sede de Seguridad Pública de Eagle Pass con los problemas de rendimiento relacionados con Gignac and Associates, LLP, en el desarrollo de la Sede de Seguridad Pública, entre otros retrasos que han surgido.
La construcción de la sede de Seguridad Pública tiene casi 8 meses de retraso debido a esas lluvias imprevistas.