Bridge Director Placido Madera explained to the council what the order change entailed and how it will now add calendar days for three separate incidents of delay.
In total, 54 days will be added to the project, which includes five days for the obtainment of additional equipment and materials for sliding pedestrian gates, additional barricades, signs, and traffic handling corresponding to the amount of calendar days added.
The estimated total cost is $20,893.31, which is being obtained from the Bridge system budget FY 2017 City of Eagle Pass Budget.
Eagle Pass Mayor Ramsey E. Cantu then asked if there were any questions or a motion for approval which was made by Councilman Luis Sifuentes, seconded by Councilwoman Yolanda Ramon.
Cantu then put the motion up for vote which passed unanimously.
Habrá demoras en proyecto del puente
El Concejo Municipal de Eagle Pass aprobó la ratificación de una orden de cambio del Proyecto de Expansión del Puente II durante su reunión especial celebrada el martes 24 de enero.
El director del puente, Plácido Madera, explicó al consejo que el cambio de orden que implicaba ahora agregar tres días separados de retraso.
En total, se añadirán 54 días al proyecto, que incluye cinco días para la obtención de equipo adicional y materiales para puertas de peatones , barricadas adicionales, letreros y manejo de tráfico correspondiente a la cantidad de días calendarios agregados.
El costo total estimado $ 20.893,31, que se obtiene del Presupuesto del sistema de Puente FY 2017 Budget de la Ciudad de Eagle Pass
El alcalde de Eagle Pass, Ramsey E. Cantu, preguntó si había alguna pregunta o una moción de aprobación que fue hecha por el concejal Luis Sifuentes, secundado por la concejal Yolanda Ramón.
Cantu entonces puso la moción para el voto que fue aprobada por unanimidad.